CPIM study guide for the nine areas of version 9.0

Certified in Planning and Inventory Management · Association for Supply Chain Management (ASCM)

Every figure below names its document; this page draws on 8 documents, last checked Nov 18, 2026.

This CPIM study guide follows the outline of ECM 9.0 area by area: what ASCM lists under each section letter, the distinctions that are easy to blur, and worked questions at the end. It is a map for your study material, not a replacement for it. If your book or course was written for version 8.0, the comparison near the end shows where its chapters land now. 1 2

Parts of this page 16 parts
  1. Where the weight sits in version 9.0
  2. Area I. Align the Supply Chain to Support the Business Strategy
  3. Area II. Conduct Sales and Operations Planning (S&OP) to Support Strategy
  4. Area III. Plan and Manage Demand
  5. Area IV. Plan and Manage Internal Supply Sources
  6. Area V. Plan and Manage External Supply Sources
  7. Area VI. Plan and Manage Inventory
  8. Area VII. Plan, Manage, and Execute Detailed Schedules
  9. Area VIII. Plan and Manage Distribution
  10. Area IX. Manage Quality, Continuous Improvement, and Technology
  11. What changed on June 1, 2026
  12. Study material: the free manual and the paid system
  13. Worked questions, one or two per area 12
  14. The rest of the CPIM pages
  15. Budgeting hours across the nine areas 3
  16. The documents behind this page

Where the weight sits in version 9.0

ASCM weights each area in percent and gives no item counts, so the bars show shares, not numbers of questions. The four planning layers in the middle, from Plan and Manage Demand to Plan and Manage Inventory, add up to roughly half of the total. The 8.0 shares sit beside them for comparison; the single 8.0 supply figure covers both supply areas of 9.0.

Share of the exam per content area, version 9.0 against version 8.0, from ASCM's CPIM content manuals.

Area
ECM 9.0 covered here
12%
10%
12%
12%
11%
14%
12%
8%
9%
ECM 8.0 2023–2026
15%
9%
9%
16% IV and V were one area
19%
16%
5%
11%
Shift in pp
−3 pp
+1 pp
+3 pp
Split: IV 12% + V 11% (23% together)
−5 pp
−4 pp
+3 pp
−2 pp
Old edition, to scale ECM 8.0

ECM 9.0 against ECM 8.0, percent by area

  1. I Strategy 15% → 12% (−3 pp)
  2. II S&OP 9% → 10% (+1 pp)
  3. III Demand 9% → 12% (+3 pp)
  4. IV Internal supply 12% ECM 8.0: merged with V, 16%
  5. V External supply 11% ECM 8.0: merged with IV, 16%
  6. VI Inventory 19% → 14% (−5 pp)
  7. VII Detailed schedules 16% → 12% (−4 pp)
  8. VIII Distribution 5% → 8% (+3 pp)
  9. IX Quality, CI & technology 11% → 9% (−2 pp)

IV–V in ECM 8.0: 16%, as the single supply area of 8.0. pp = percentage points.

CPIM ECM 9.01 CPIM 9.0 FAQ2 CPIM ECM 8.03

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2 CPIM ECM 8.03

Area I. Align the Supply Chain to Support the Business Strategy

Section A starts from the business environment: how a company competes, which order winners and order qualifiers its markets reward, and where the push-pull boundary sits for make-to-stock, assemble-to-order, make-to-order and engineer-to-order products. Section B moves to functional strategy, core competencies and make-or-buy. Section C covers process design, from the product-process matrix to layouts, and section D the measures that tell a planner whether the strategy is working, cash-to-cash cycle time among them. Sections E and F add supply chain risk and sustainability goals.

The push-pull boundary and the customer order decoupling point are the same idea seen from two sides. Upstream of it, work runs to a forecast; downstream, it waits for a customer order. Moving it changes lead time to the customer and the inventory you hold at once.

A qualifier wins nothing on its own

An order qualifier is the level a supplier must reach just to be considered, such as an acceptable quality standard. Meeting it keeps you on the list; the order goes to whoever beats rivals on the winner, often price or speed. A qualifier that slips can lose the business even when the winner is strong.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area II. Conduct Sales and Operations Planning (S&OP) to Support Strategy

The S&OP area places the process in the planning hierarchy: below the business plan, above the master schedule, monthly, over a horizon of a year or more and in product families rather than items. Section B builds the aggregate demand plan, including the product portfolio and new launches. Section C builds the aggregate supply plan and the resource plan that checks it; chase, level and hybrid production strategies live here. Section D reconciles portfolio, demand, supply and financial plans into one set of numbers the executive team signs off.

What matters is the level of detail each plan works at. S&OP settles volume by family; how that volume splits into individual items and options is the master scheduler's job, one level down.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area III. Plan and Manage Demand

Demand opens with the customer: needs and specifications, segmentation, point-of-sale and collaboration data, and the delivery measures customers judge you by. Marketing and product management bring promotions and product configuration into the plan. Sources of demand separate independent demand, which is forecast, from dependent demand, which is calculated from a parent's schedule and bill of material. Section D covers qualitative and quantitative forecasting methods, horizons and time buckets, and section E the measures of forecast performance.

Three error measures recur. Mean absolute deviation (MAD) is the average size of the errors in units, ignoring sign. Mean absolute percentage error (MAPE) puts the same idea in relative terms, so it compares items of very different volume. The tracking signal divides the running sum of forecast errors by MAD; it grows when the errors keep leaning one way.

Dependent demand is calculated, not forecast

Components and subassemblies get their quantities from the parent's schedule and the bill of material. Forecasting them separately adds error that MRP would not have made. The exception is a component that is also sold as a service part: that portion is independent and is forecast alongside the calculated requirement.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area IV. Plan and Manage Internal Supply Sources

Internal supply is the classic planning chain inside the plant. Section A is master scheduling: production environments, the master production schedule, planning bills, two-level master schedules, engineering changes and new or ending products, with projected available balance and available-to-promise records. Section B is the rough-cut capacity plan, which tests the MPS against a few key resources through a bill of resources. Section C is MRP: the time-phased record, gross-to-net logic, lot sizing, lead-time offsetting, action messages and the closed loop. Sections D to F cover final assembly scheduling, product costs and how to absorb changes and disruptions, time fences included.

The MRP record runs the same way every time: gross requirements, less on-hand and scheduled receipts, give net requirements; lot sizing turns them into planned order receipts; offsetting by lead time places the planned order releases, which become the gross requirements of the next level down.

Rough-cut is not detailed capacity

Rough-cut capacity planning checks the master schedule against key work centers only. Capacity requirements planning comes later and works from MRP's planned orders plus open shop orders, run through routings for every work center.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area V. Plan and Manage External Supply Sources

External supply is the area that version 9.0 split off on its own. Section A covers supplier selection: the categories of supply risk, single and multiple sourcing, and supplier certification. Section B covers supplier relationship management, from transactional buying to partnerships, with performance scorecards, contract terms and data sharing. Section C turns to purchasing methods and release methods such as blanket orders, kanban signals and vendor-managed inventory, together with transport modes and third- and fourth-party logistics providers. Section D handles supplier changes and disruptions.

The CPIM view of a supplier is a planner's view: how purchase lead time, order release and supplier reliability feed the material plan. The wider sourcing questions of category strategy and global networks sit closer to ASCM CSCP.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area VI. Plan and Manage Inventory

Inventory is the largest area in 9.0. Section A sets targets for service and financial goals and sorts stock by type, class and ABC segment. Section B covers replenishment, both push and pull, with order point, periodic review, economic order quantity and safety stock, plus MRO and items that need special handling. Section C prices inventory: carrying, ordering and stockout costs, valuation by FIFO, LIFO, average or standard cost, turns and days of supply. Section D is control: location systems, cycle counting, record accuracy and traceability. Section E deals with returns and disposition.

The economic order quantity is the square root of twice the annual demand times the cost per order, divided by the annual carrying cost per unit; at that quantity, yearly ordering and carrying costs are equal. The order point is demand during lead time plus safety stock, which is set from the variability of demand over that lead time.

ABC ranks dollars, not units

ABC classification sorts items by annual dollar usage, unit cost times yearly quantity. A cheap fastener used by the million can be an A item; an expensive part bought twice a year can be a C. Count frequency and tolerance usually follow the class.

Push and pull are about the trigger

In a push system, a schedule or forecast releases material before anyone downstream asks for it. In a pull system, consumption downstream sends the signal, a kanban card or an empty bin. A plant can push to the decoupling point and pull after it, so the label depends on which part of the flow you look at.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area VII. Plan, Manage, and Execute Detailed Schedules

This area turns plans into work on the floor. Section A plans detailed schedules: flow rate, sequencing, bottlenecks managed with drum-buffer-rope, and demand that does not fit the standard flow. Section B creates production and labor schedules, using theoretical, demonstrated and rated capacity, load, forward and backward scheduling, simulation, line balancing and a capacity cushion. Section C executes and controls them through production activity control: order release, routings, queue management, exceptions and backflushing.

Manufacturing lead time is the sum of queue, setup, run, wait and move time, and queue is often the biggest piece, which is why input/output control watches queues. Dispatching rules decide which waiting job runs next; the critical ratio divides the time left until the due date by the work left, so a value below 1 means the job is behind.

Forward and backward start from different ends

Backward scheduling starts at the due date and works back to the latest start, which keeps work in process low but leaves no slack. Forward scheduling starts now and finds the earliest finish, which shows whether a date can be met at all. A start date that falls in the past under backward scheduling means the order is already late.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area VIII. Plan and Manage Distribution

Distribution is the smallest area, with two sections. Section A plans distribution: network trade-offs between service, inventory and transport cost, distribution requirements planning, and inbound and outbound flows. Section B manages customer orders: replenishment of the field locations, order management, tracking and tracing, and the measures of delivery performance.

Distribution requirements planning applies MRP's time-phased logic to a network of warehouses. Each branch nets its forecast against stock and in-transit receipts, and its planned orders, offset by transit time, add up as gross requirements at the location that supplies it, usually a central warehouse or the plant's master schedule.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

Area IX. Manage Quality, Continuous Improvement, and Technology

The last area has three parts. Section A is quality management, including the cost of quality and process capability. Section B is continuous improvement, with Lean and Six Sigma among its methods. Section C is technology for planning and execution, from ERP and advanced planning and scheduling to newer tools.

The CPIM angle stays on planning: how waste, variation and poor data show up as longer lead times, extra buffers and unreliable schedules, and which system holds which planning task. Cost of quality splits into money spent preventing defects, money spent finding them, and the cost of failures caught inside the plant and outside it; spending more on the first two usually shrinks the last two.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2

What changed on June 1, 2026

Version 9.0 took over from 8.0 that day, with no overlap; the opening chart shows every shift.

Supply gained the most ground: one area in 8.0, two areas with 12% and 11% in 9.0. Inventory and detailed schedules gave up the most. For an 8.0 book this means its single supply chapter now feeds two areas, and supplier selection, relationships and purchasing deserve more hours than it gave them.

Fact As the documents put it Source
Content manual followed here Exam Content Manual version 9.0, in force since June 1, 2026. CPIM ECM 9.01 CPIM 9.0 FAQ2
Version change Version 9.0 replaced 8.0 on June 1, 2026, the day after the last 8.0 sittings; the two never ran side by side. ASCM published the 9.0 manual on November 4, 2025 and began selling 9.0 study materials on February 3, 2026. CPIM 9.0 FAQ2 CPIM ECM 9.01
Previous content manual ECM 8.0, used from June 1, 2023 through May 31, 2026, in eight areas: strategy 15%, S&OP 9%, demand 9%, supply 16%, inventory 19%, detailed schedules 16%, distribution 5%, and quality, continuous improvement and technology 11%. Version 9.0 split the one supply area into internal and external supply sources, 23% together against 16%. Inventory fell from 19% to 14% and detailed schedules from 16% to 12%; demand rose from 9% to 12% and distribution from 5% to 8%. CPIM ECM 8.03 CPIM ECM 9.01
From two exams to one A single exam since version 8.0 opened on June 1, 2023; version 7.0 had two, Part 1 and Part 2. February 1, 2024 was the final day to sit either 7.0 part. ASCM handbook 20234 CPIM ECM 9.01
Job task analysis A 2024 job task analysis built on survey answers from more than 1,800 professionals. CPIM ECM 9.01

From ASCM's CPIM Exam Content Manuals 8.0 and 9.0, its FAQs on the move to version 9.0 and the January 2023 exam handbook, read November 18, 2026.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2 CPIM ECM 8.03 ASCM handbook 20234

Study material: the free manual and the paid system

ASCM's own material comes in two tiers. The CPIM Exam Content Manual is free and holds the outline, the key terms, the reference list and a handful of sample questions; it is the document every section above is drawn from. The Learning System is optional, priced like the exam itself (see the table), and it is organized in nine modules, one for each area.

Courses from ASCM chapters, universities and training firms are sold separately. Whatever you use, check that its contents follow the nine areas, and split your hours roughly by the weights. ASCM suggests about 100 hours of study for each of its certification exams, as an average rather than a rule.

Fact As the documents put it Source
Prep from ASCM The free CPIM Exam Content Manual, with outline, key terms, references and 10 sample questions, and the paid Learning System. ASCM offers a 30-day free trial of Learning System Module 1. CPIM ECM 9.01 CPIM program page5
Learning System price Optional and sold apart from the exam, at $1,265 with the upgrade or $1,755 without. It comes with 12 months of online access and printed books. ASCM states that no CPIM exam question is taken from it. CPIM program page5 ASCM handbook 20266 CPIM ECM 9.01
Learning System modules Nine Learning System modules, one for each content area of version 9.0. CPIM module outline 20267 CPIM program page5
Suggested study time About 100 hours, ASCM’s average recommendation for each certification exam. ASCM scoring page8

From ASCM's CPIM program page (archived October 24, 2026), the 2026 Learning System module outline, the exam details page (archived August 10, 2026) and the content manual 9.0. Prices and the bundle: registration.

Documents behind this part: ASCM scoring page8 CPIM ECM 9.01 CPIM program page5 ASCM handbook 20266 CPIM module outline 20267

Worked questions, one or two per area

Tally: 0/12 tried, 0 on the key
I Strategy · 12% Question 1 of 12

Demand for a product is stable and predictable, but its supply base is new, with unreliable yields and frequent disruptions. Which supply chain strategy fits best?

Choose a letter to record your answer; each option then opens with its reasoning.

  1. An agile supply chain Check A
    Off the key. An agile chain answers uncertainty on both the demand and the supply side; here demand is predictable, so agility pays for a risk that is absent.
  2. An efficient chain Check B
    Off the key. An efficient chain suits stable demand only when supply is stable too; a lean, cost-driven flow breaks down when yields and deliveries are unreliable.
  3. A risk-hedging chain Check C
    This is the keyed answer. Stable demand with an unreliable, still-developing supply base is the risk-hedging case: pool inventory and share sources so supply failures do not reach the customer.
  4. A responsive chain Check D
    Off the key. A responsive chain fits unpredictable demand with a stable supply base, the reverse of this situation.
You chose—
Key—
Outcome—
II S&OP · 10% Question 2 of 12

The S&OP supply review finds a 10% capacity shortfall in the three peak months of a storable, seasonal product family. Which option lets the plant make the full seasonal volume itself without adding capacity?

  1. Hire temporary workers for the peak season Check A
    Off the key. Temporary workers add labor capacity for the season, which the stem rules out, and they bring hiring and training costs.
  2. Subcontract part of the volume during the peak months Check B
    Off the key. Subcontracting moves part of the volume to an outside supplier, so the plant no longer makes the full seasonal volume itself.
  3. Schedule overtime during the three peak months Check C
    Off the key. Overtime adds hours of capacity in the peak months, so it is a capacity increase rather than a way to avoid one.
  4. Build anticipation inventory in the preceding months Check D
    This is the keyed answer. Building anticipation inventory works because the product stores well: spare capacity in the months before the peak makes stock that is drawn down during the peak, with no capacity added.
You chose—
Key—
Outcome—
III Demand · 12% Question 3 of 12

Sales reps' territory forecasts run consistently above actual demand. What is the best corrective step?

  1. Feed back each rep's own measured forecast bias Check A
    This is the keyed answer. Measuring each rep's bias and showing it to that rep corrects the source of the error while keeping the market knowledge that sales input brings.
  2. Drop sales input in favor of a statistical model Check B
    Off the key. Dropping sales input throws away customer and market knowledge that history cannot see; the problem is bias, which can be measured and corrected.
  3. Average the sales input with the finance plan Check C
    Off the key. Averaging sales input with the finance plan mixes a target with a forecast and leaves each rep's bias in the numbers, only diluted.
  4. Cut every rep's forecast by a fixed 10% Check D
    Off the key. A fixed 10% haircut assumes every rep overforecasts by the same amount, so accurate reps end up too low and the worst offenders stay high.
You chose—
Key—
Outcome—
IV Internal supply · 12% Question 4 of 12

A sales rep sees 600 units on hand for SKU-750. Of these, 450 are already allocated to earlier customer orders, and a 200-unit receipt is due in 12 days. How many units can be promised for shipment within 7 days?

  1. 350 units Check A
    Off the key. 350 adds the 200-unit receipt, but it arrives in 12 days and cannot cover a shipment within 7 days.
  2. 600 units Check B
    Off the key. 600 is the total on hand and ignores the 450 units already allocated to earlier orders.
  3. 150 units Check C
    This is the keyed answer. Only uncommitted stock counts: 600 on hand minus 450 allocated leaves 150, and the receipt due in 12 days falls outside the 7-day window.
  4. 800 units Check D
    Off the key. 800 counts all stock plus the late receipt and ignores the allocations, so it overpromises by 650 units.
You chose—
Key—
Outcome—
V External supply · 11% Question 5 of 12

A critical component comes from a single overseas supplier, and port closures of up to three weeks occur. Demand is stable. Which inventory approach best addresses this risk?

  1. A strategic buffer sized to the disruption Check A
    This is the keyed answer. The risk is a known outage of up to three weeks, so a buffer sized to cover that outage protects supply in a way everyday safety stock was never built to do.
  2. Safety stock based on normal demand variability Check B
    Off the key. Safety stock set for everyday demand swings covers days of variation, not a three-week supply stop, and demand here is already stable.
  3. A larger order quantity to reduce orders Check C
    Off the key. Ordering less often changes the cycle stock between orders, but a closure that hits after that stock is used up still stops supply.
  4. A shorter review period for the component Check D
    Off the key. Reviewing more often catches demand changes sooner, but no review frequency moves parts through a closed port.
You chose—
Key—
Outcome—
VI Inventory · 14% Question 6 of 12

A buyer switches an imported component from ocean freight (30 days in transit) to air freight (3 days). Which type of inventory is most directly reduced?

  1. Cycle stock Check A
    Off the key. Cycle stock depends on order size, which stays the same when only the freight mode changes.
  2. Pipeline inventory Check B
    This is the keyed answer. Stock in transit is pipeline inventory, and its average quantity scales with transit time, so cutting 30 days to 3 removes most of it.
  3. Decoupling inventory Check C
    Off the key. Decoupling inventory sits between operations so each can run at its own pace; it is not stock on the way from a supplier.
  4. Anticipation inventory Check D
    Off the key. Anticipation inventory has nothing to do with transport, so a change of freight mode leaves it untouched.
You chose—
Key—
Outcome—
VI Inventory · 14% Question 7 of 12

A DC item's mean absolute deviation (MAD) of lead-time demand is 160 units, and forecast errors are normally distributed. Management raises the target service level from 95% (z = 1.65) to 99% (z = 2.33). How much additional safety stock is required?

  1. 109 Check A
    Off the key. 109 multiplies the z difference by the MAD itself (0.68 × 160) and skips the 1.25 conversion from MAD to standard deviation.
  2. 136 Check B
    This is the keyed answer. With σ ≈ 1.25 × MAD = 200 units, the added safety stock is (2.33 − 1.65) × 200 = 0.68 × 200 = 136 units.
  3. 330 Check C
    Off the key. 330 is the whole safety stock at 95% (1.65 × 200), not the increase needed to reach 99%.
  4. 466 Check D
    Off the key. 466 is the whole safety stock at 99% (2.33 × 200); the question asks only for the amount added.
You chose—
Key—
Outcome—
VII Detailed schedules · 12% Question 8 of 12

A customer suddenly needs 100 units of a 400-unit shop order two days earlier than planned. Which action best meets the need with the least disruption to other work?

  1. Rush a split lot of 100 units ahead Check A
    This is the keyed answer. Splitting off the 100 needed units and moving them ahead gets them out early while the other 300 keep their place, so other work is barely disturbed.
  2. Release a separate new order for 100 units Check B
    Off the key. A new 100-unit order needs its own material, setups, and queue time from the start, so it is slower and adds load instead of using the order already in process.
  3. Expedite the whole 400-unit order Check C
    Off the key. Expediting all 400 units pushes 300 that nobody needs early ahead of other jobs, which disrupts the most work.
  4. Add overtime at every routing work center Check D
    Off the key. Overtime at every center adds cost and hours across the shop when only 100 units need to move faster.
You chose—
Key—
Outcome—
VIII Distribution · 8% Question 9 of 12

A customer orders an item that is out of stock at the nearest DC but available at a second DC that is 4 days' transit from the customer. The customer's due date allows 5 days. What should customer service do?

  1. Decline the order as out of stock Check A
    Off the key. The network holds stock that meets the due date, so declining the order gives up a sale for no reason.
  2. Transfer stock from the second DC to the nearest DC Check B
    Off the key. Moving the second DC's stock to the nearest DC first adds a handling step and a second shipment, so delivery comes later than the 4-day direct route and costs more.
  3. Backorder at the nearest DC until it is replenished Check C
    Off the key. A backorder waits for a replenishment of unknown timing while usable stock sits at another DC that can meet the date.
  4. Promise delivery from the second DC Check D
    This is the keyed answer. Shipping from the second DC uses stock that exists now and arrives in 4 days, inside the 5 the due date allows, with no extra handling.
You chose—
Key—
Outcome—
IX Quality, CI & technology · 9% Question 10 of 12

A plant wants real-time visibility of which operation each order is at, and electronic dispatching of work to each workstation. Which system provides this?

  1. The MRP module of the ERP system Check A
    Off the key. MRP plans material by time bucket and has no real-time view of which operation an order is at.
  2. Warehouse management system Check B
    Off the key. A WMS runs storage locations, picking, and shipping in the warehouse, not the operations on the production floor.
  3. Advanced planning and scheduling Check C
    Off the key. Advanced planning and scheduling builds finite-capacity schedules; it plans the work rather than tracking where each order physically is or dispatching to stations in real time.
  4. Manufacturing execution system Check D
    This is the keyed answer. A manufacturing execution system follows each order operation by operation on the shop floor and sends work to stations electronically, which is the visibility the plant wants.
You chose—
Key—
Outcome—
IV Internal supply · 12% Question 11 of 12

A supplier will stop making a component. Demand for it over the rest of the product's life is forecast at 960 units, and the planner adds a 10% allowance to that forecast. The plant has 200 units on hand. How many units should be ordered as a lifetime buy?

  1. 1,056 units Check A
    Off the key. 1,056 is the total need with the allowance but does not subtract the 200 units on hand.
  2. 856 units Check B
    This is the keyed answer. The need is 960 × 1.10 = 1,056 units, and 200 are already on hand, so the lifetime buy is 856.
  3. 760 units Check C
    Off the key. 760 subtracts stock on hand but drops the 10% allowance the planner added.
  4. 836 units Check D
    Off the key. 836 applies the allowance after subtracting stock, (960 − 200) × 1.10, instead of to the full forecast.
You chose—
Key—
Outcome—
VII Detailed schedules · 12% Question 12 of 12

In week 2, work center DRILL has a nominal capacity of 160 hours, reduced by a scheduled 24-hour maintenance block. The CRP load for the week is orders A (48 hours), B (36 hours) and C (32 hours), plus 6 hours of setup. What is the load as a percentage of capacity?

  1. 85.3% Check A
    Off the key. 85.3% drops the 6 setup hours from the load (116 ÷ 136), but setup time is part of the load.
  2. 111.5% Check B
    Off the key. 111.5% inverts the ratio (136 ÷ 122); the measure is load divided by capacity.
  3. 89.7% Check C
    This is the keyed answer. Available capacity is 160 − 24 = 136 hours and the load is 48 + 36 + 32 + 6 = 122 hours, so the load is 122 ÷ 136 = 89.7%.
  4. 76.3% Check D
    Off the key. 76.3% divides the load by the nominal 160 hours and ignores the maintenance block.
You chose—
Key—
Outcome—

The rest of the CPIM pages

Budgeting hours across the nine areas

Can I prepare for CPIM 9.0 with a Learning System bought for 8.0?

Partly. The planning concepts largely carry over, but the structure does not: 9.0 has nine areas instead of eight, gives external supply its own area and moves weight away from inventory and detailed schedules. If you use older material, read the 9.0 content manual alongside it and fill the gaps from there.

Which CPIM content area deserves the most study time?

By weight, Plan and Manage Inventory, at 14% of the exam. Weight is only half the answer, though: the diagnostic section of your score report, or a weak result on the practice set, tells you where your own gaps are.

Is the ASCM Supply Chain Dictionary allowed during the exam?

No. It is a study reference, and the content manual's key terms follow its definitions, but it stays outside the testing room. The full list of permitted items is on the registration page.

Documents behind this part: CPIM ECM 9.01 CPIM 9.0 FAQ2